Bend weekly road and traffic report: Week of May 25-31

City of Bend

BEND, Ore. (KTVZ) -- Here's the city of Bend's weekly road and traffic report for the week of May 25-31:

  • SE 15th Street between the new collector road and SE Gateway Drive for regrading of roadway, single lane closure with flagging, 5/18/20 - 6/7/20, 9 a.m. – 3:30 p.m.

Ongoing Closures:

  • SE Greenmont Drive between SE Desert Woods Drive and SE Hill Ridge Drive for infrastructure installation in relation to a neighborhood extension project, full road closure with local access only, began 5/4/20
  • Murphy Road between Brown Trout Place and Country Club Drive for roadwork related to Murphy Corridor project, bypass road constructed to provide westbound/eastbound traffic with minimal impacts, 4/17/20 - 06/12/20
  • King Solomon Court from SE King Hezekiah Way for infrastructure installation in relation to a neighborhood extension project, full road closure with local access only, began 3/13/20
  • NE 27th Street between NE Butler Market and Jill Avenue for roadwork related to roundabout construction, full road closure with detour, 4/13/20 - 7/27/20
  • NE Butler Market Road between NE 27th Street and NE Marys Grace Lane for roundabout construction, full road closure with detour, began 4/13/20
  • SE Deschutes Market Road between NE Butler Market Road and Monticello Drive for roundabout construction, full road closure with detour, began 4/13/20
  • SE Knott Road between Brosterhous Road and SE Raintree Drive for construction of a new roundabout at Knott Road and 15th Street intersection, bypass road to be constructed with local access to Tekampe Road, began 3/16/20
  • SE 15th Street between Knott Road and the new collector road for infrastructure installation, full closure of the roadway, 12/26/20 - 7/31/20
  • NE Butler Market Road between Deschutes Market Road and Eagle Road for roundabout construction, full road closure with detour, began 4/3/20
  • SE Desert Woods Drive between Greenmont Drive and 15th Street for infrastructure installation in relation to a neighborhood extension project, full road closure with local access only, began 3/11/20

Future Closures:

  • 15th Street between Desert Woods drive to Hollis Lane for infrastructure installation on the Neighborhood Extension Project, southbound lane closure with northbound lane to remain open, work begins 6/15/20.
  • NW 13th Street between NW Kingston Avenue and NW Jacksonville Avenue for infrastructure installation, full road closure, 6/1/20 - 6/12/20, 7 a.m. – 4 p.m.

Work schedules are dependent on weather conditions and other factors.

Contact: Kyle Thomas, Construction Manager

541-323-8519, kthomas@bendoregon.gov

For Street Preservation related questions: Paul Neiswonger, Streets Supervisor

541-317-3035, pneiswonger@bendoregon.gov

Closures and detours in Bend are updated weekly at: www.bendoregon.gov/traffic

Find more information about street operations at: www.bendoregon.gov/streetpreservation

Weekly reports can be received via email by subscribing to Weekly Road and Traffic Reports at: www.bendoregon.gov/enews

Article Topic Follows: Community Billboard

Jump to comments ↓

KTVZ news sources

BE PART OF THE CONVERSATION

KTVZ NewsChannel 21 is committed to providing a forum for civil and constructive conversation.

Please keep your comments respectful and relevant. You can review our Community Guidelines by clicking here

If you would like to share a story idea, please submit it here.

Skip to content