Tumalo paving projects set to begin
On Monday, May 19, construction crews will begin work on the asphalt overlay for the following roads in Deschutes County:
Cook Avenue from Highway 20 to Tumalo Road: Construction will occur from Monday, May 19 to Wednesday, May 21. This work will occur at night from the hours of 7:00 p.m. to 7:00 a.m.
Graystone Lane, Tumalo Place and Deschutes Pleasant Ridge Road: Construction will occur from Tuesday, May 27 to Friday, May 30. This work will occur at night from the hours of 7:00 p.m. to 7:00 a.m.
Traffic will be limited to one lane and drivers can expect delays of up to 20 minutes during construction. Drivers should use alternate routes where possible. For more information, call George Kolb, Deschutes County Road Department at (541) 322-711