Skip to Content

ODOT Region 4 construction update: Week of June 25

KTVZ

Here’s the ODOT Region 4 weekly road construction update for the week of June 25:

The Oregon Department of Transportation is committed to providing a safe, efficient transportation system. ODOT invests in Oregon’s future through roadway improvement projects. The following projects are located in ODOT’s Region 4 encompassing Central Oregon from The Dalles to Klamath Falls on the east side of the Cascades.

All work is dependent on weather conditions and schedules are subject to change.

Where traffic is routed through or around a work zone, pedestrians, including those with disabilities, will also be provided alternate routes through the work zone.

Crook County

OR 126 @ Tom McCall Roundabout – Alex Hodge Construction will be paving and striping connecting roads at night. There will be one-way traffic and flaggers, and delays of up to 20 minutes. The Contractor will also be working on light poles, planter strips and bioretention ponds, and removing old pavement during the day. No traffic impacts are expected during the day.

Deschutes County

US 97: Sunriver Interchange to OR 31 – Roy Houck Construction will continue excavating and installing sidewalks and ramps on the westside of US 97 in La Pine. There will be shoulder closures and slow traffic.

US 20 @ Barclay Drive – Knife River will be constructing a trail along US 20 southeast of the roundabout. Minimal traffic impacts are expected.

US 20: Jack Lake Road to Pine Street (Sisters) – Oregon Mainline Paving is crushing rock at the Hogg Rock Quarry and stockpiling it across the highway. The right lane of eastbound 20 may be closed between MP 79.5 and 79.8. Grinding and paving is scheduled to start in early July.

Jefferson County

US 97: US 26 Jct. to NW 10th Street (Madras – Terrebonne) – Knife River will be installing additional traffic control measures Sunday night and grinding and inlay paving SB 97 working north from 10th St in Terrebonne Monday through Thursday nights. There will be one-way traffic with flaggers and pilot cars between 7 pm and 7 am, with traffic delays of up to 20 minutes.

US 97: Spanish Hollow Creek & Trout Creek Bridges – Stellar J Construction is performing bridge replacement work. There may be one-way traffic with flaggers anytime. After the flagging is complete the construction zone will be switched over and controlled with signals.

Klamath County

OR 140: Buck Creek Bridge – Marcum & Sons Construction is beginning work to replace the Buck Creek Bridge (MP 22). Traffic will be controlled by a temporary signal and limited to a single lane. Work will take place Monday through Friday during daytime hours. Drivers can expect delays up to 10 minutes.

OR 240: Greensprings Interchange to Klamath Falls/Malin Hwy – Rocky Mountain Construction will be completing shoulder work, installing signs and concrete sidewalk. Minor delays are expected.

US 97: Algoma Road to Miller Island Road – Rocky Mountain Construction will be completing barrier, guardrail, earthwork and shoulder work at night between the hours of 7pm and 7am. The work zone will be controlled with flaggers and pilot cars. Drivers can expect delays up to 20 minutes.

US 97: Spring Creek Hill to Modoc Point – Rocky Mountain Construction will be paving between the hours of 7pm and 7am, Sunday night through Friday morning. The work zone will be controlled with flaggers and pilot cars. Drivers can expect delays up to 20 minutes.

Lake County

US 395: South Fork Crane Creek – Marcum & Sons will be onsite completing survey, culvert and earthwork. Expect minor delays.

Sherman County

US 97: Spanish Hollow Creek & Trout Creek Bridges – Stellar J Construction is completing drilled shaft construction access on US 97 over Spanish Hollow Creek. There may be one-way traffic with flaggers Sunday through Saturday anytime.

US 97: Shaniko to Trout Creek – High Desert Aggregate and Paving will be onsite performing shoulder work from MP 58-59 on US97. The contractor will have flaggers in place at construction site to control traffic while trucks enter and exit the highway. Expect minimal delays.

Wasco County

I-84: Hood River to Tower Road – Oregon Mainline Paving will be onsite this week the night of Thursday June 28th to layout payment striping and there will be single lane closures in the East and West Bound Directions. Expect no delays.

Wheeler County

Fossil Heritage Trail – Construction will take place Monday through Friday during daytime hours. The contractor may hold traffic on flagging operations for up to 20 minutes. Use alternate routes and expect delays when traveling through the listed areas of construction.

Various

Region 4 Curve Warning Signs – Baker Rock Resources will be installing sign bases on the Ochoco Highway (US 26). There may be one-way traffic with flaggers and delays of up to 20 minutes.

Article Topic Follows: News

Jump to comments ↓

KTVZ News Team

BE PART OF THE CONVERSATION

KTVZ NewsChannel 21 is committed to providing a forum for civil and constructive conversation.

Please keep your comments respectful and relevant. You can review our Community Guidelines by clicking here

If you would like to share a story idea, please submit it here.

Skip to content