Watch for utility work near downtown Bend this week, as Cascade Natural Gas crews continue the Bend Westside Replacement Project.

One crew will be working in the alley between Northwest Florida and Georgia avenues, installing a 2-inch gas main. NW Georgia and the alley between Florida and Georgia will remain closed to through traffic between 7 a.m. and 5:30 p.m.

At the same time, a paving crew will be on NW Shasta Place, starting at the intersection with NW Delaware Avenue, and will work south towards NW Riverside Boulevard.

Then, on Thursday, the paving crew will start at the intersection of Shasta Place and Riverside, paving northwest on Riverside.

Affected streets will remain closed to through traffic from 7 a.m. to 5 p.m., but will be open each evening.

Residents are encouraged to seek alternate routes to avoid congestion.

Article Topic Follows: News

Jump to comments ↓

KTVZ News Team

BE PART OF THE CONVERSATION

KTVZ NewsChannel 21 is committed to providing a forum for civil and constructive conversation.

Please keep your comments respectful and relevant. You can review our Community Guidelines by clicking here

If you would like to share a story idea, please submit it here.

Skip to content