City of Bend road and traffic report: Week of May 11-17
Ongoing Closures:
- SE 3rd Street between Division Street and Reed Lane for the safety crossing project, expect daytime lane closures including the middle left turn lane with business driveway access right in/right out only during this time, 4/27/20 - 5/15/20, 6 a.m. – 5 p.m.
- Murphy Road between Brown Trout Place and Country Club Drive for roadwork related to Murphy Corridor project, Bypass road constructed to provide Westbound/Eastbound traffic with minimal impacts to traffic, 4/17/20 - 06/12/20
- SE Glenwood Drive between SE 5th Street and NE 9th Street for infrastructure installation, single lane closure with flagging, 4/15/20 - 5/13/20, 9 a.m. – 4 p.m.
- NE 27th Street between NE Butler Market and Jill Avenue for roadwork related to roundabout construction, full road closure with detour, 4/13/20 - 7/27/20
- NE Butler Market Road between NE 27th Street and NE Marys Grace Lane for roundabout construction, full road closure with detour, begins 4/13/20
- Deschutes Market Road between NE Butler Market Road and Monticello Drive for roundabout construction, full road closure with detour, begins 4/13/20
- Knott Road between Brosterhous Road and SE Raintree Drive for construction of a new roundabout at Knott Road and 15th Street intersection, bypass road to be constructed with local access to Tekampe Road, began 3/16/20
- 15th Street between Knott Road and the new collector road for infrastructure installation, full closure of the roadway, 12/26/20 - 7/31/20
- NE Butler Market Road between Deschutes Market Road and Eagle Road for roundabout construction, full road closure with detour, began 4/3/20
- Desert Woods Drive between Greenmont Drive and 15th Street for infrastructure installation in relation to a neighborhood extension project, full road closure with local access only, began 3/11/20
Future Closures: - 15th Street between Desert Woods Drive to Hollis Lane for infrastructure installation on the Neighborhood Extension Project, southbound lane closure with northbound lane to remain open, work begins 6/15/20.
Work schedules are dependent on weather conditions and other factors.
Contact: Kyle Thomas, Construction Manager
541-323-8519, kthomas@bendoregon.gov
For Street Preservation related questions: Paul Neiswonger, Streets Supervisor
541-317-3035, pneiswonger@bendoregon.gov
Closures and detours in Bend are updated weekly at: www.bendoregon.gov/traffic
Find more information about street operations at: www.bendoregon.gov/streetpreservation
Weekly reports can be received via email by subscribing to Weekly Road and Traffic Reports at: www.bendoregon.gov/enews