Bend road construction, traffic report: Week of May 20
Here is the city of Bend’s weekly road and traffic report for May 20-26:
·NW Greeley Avenue between NW Harriman Street and Bend Parkway for paving, road closure with local access only, 5/20/19.
·NW Irving Avenue between NW Oregon Avenue and Bend Parkway for paving, road closure with local access only, 5/20/19.
·McClellan Road west of Brookswood Boulevard for paving, road closure with local access only, 5/21/19.
·NE 2nd Street between NE Burnside Avenue and NE Quimby Avenue for paving, road closure with local access only, 5/22/19.
·NW Twilight Drive, NW Nightfall Circle, Sample Court, NW Keenan Court, and NW Fitzgerald Court for milling, road closure with local access only,5/20/19 – 5/24/19.
·NW Franklin Avenue between NW Broadway Street and NW Wall Street for paving Mirror Pond Parking Lot, single lane closure with flaggers, 5/20/19 -5/21/19, night work from 8:00 p.m. – 8:00 a.m.
·Butler Market Road between NE Broken Bow Drive and NE Sandy Drive for utility work, lane shifts and single lane closures with flagging, 5/20/19, 9 a.m. – 3 p.m.
·SE Cessna Drive between SE Piper Drive and SE Craven Road for waterline installation, road closure with detour, 5/20/19 – 6/6/19.
·15th Street at intersection with Golden Gate Place for utility potholing, single lane closures with flaggers, 5/21/19 – 5/23/19, 9 a.m. – 3 p.m.
Ongoing Closures:
·Roundabout at intersection of NW Shevlin Park Road and NW Mt. Washington Drive for roundabout reconstruction, road closure with detours, 5/13/19 -6/27/19.
·NE 6th Street between NE Greenwood Avenue (US Hwy 20) and NE Majesty Lane for asphalt speed hump installation, pavement markings, and concrete work at several intersections, rolling one block closures and detours along with day time flagging, 4/29/19 – 6/15/19.
·Brosterhous Road between American Lane and Jacklight Lane for sewer main installation, southbound lane closures with detours, until 7/15/19.
Upcoming Closures:
·The intersection of Empire Avenue and Purcell Boulevard will be closed to complete the construction of a new roundabout at this intersection. The closure will begin on Monday, June 17th and will last approximately 8 weeks. Access to Terrango Glen and Lava Ridges neighborhoods will be maintained during construction. Detours will be signed and a map showing these detours will be issued in future outreach efforts. Please be aware of construction speed limit changes in this area.
·SW Bond Street between SE Wilson Avenue and SW Upper Terrace Drive for paving, road closure with detour, 5/28/19.
·Wilderness Way, Steens Mountain Loop, Strawberry Mountain Court, Cultus Mountain Court, Steens Mountain Court, Merritt Court, and Dooley Mountain Loop for milling and paving, road closures with local access only, 5/28/19 – 5/30/19.
·SW Troon Avenue and NW 17th Avenue for milling and paving, road closures with local access only, 5/28/19.
·Providence Drive north of Neff Road for milling and paving, road closure with local access only, 5/30/19 – 5/31/19.
·Providence Drive between Neff Road and Highway 20 for milling and paving, road closure with local access only, 5/30/19 – 5/31/19.
·Fairway Drive between Country Club Drive and Parr Lane for milling, road closure with local access only, 5/31/19.
Work schedules are dependent on weather conditions and other factors.