ODOT Region 4 road construction update: Week of June 24

KTVZ

Here is the Oregon Department of Transportation’s Region 4 weekly road construction update for the week of June 24:

The Oregon Department of Transportation is committed to providing a safe, efficient transportation system. ODOT invests in Oregon’s future through roadway improvement projects. The following projects are located in ODOT’s Region 4 encompassing Central Oregon from The Dalles to Klamath Falls on the east side of the Cascades.

All work is dependent on weather conditions and schedules are subject to change.

Where traffic is routed through or around a work zone, pedestrians, including those with disabilities, will also be provided alternate routes through the work zone.

Deschutes County

All Roads Transportation Safety (Various County Roads) – The contractor will be installing delineators and cutting center-line rumble strips on South Century Drive during daytime hours. Traffic should expect single lane closures controlled by flaggers with delays of up to 20 minutes.

Klamath County

OR140 : Green Springs Intch – Klamath Falls/ Malin Highway Section (South Klamath Falls Highway) – MP 0 – MP 5.97; No work or delay expected on this project this week.

OR 140: OR 39 Junction – Olene (Klamath Falls – Lakeview Highway) – striping and cleanup work. Work zone controlled by flagging and pilot car, expect 20 minute delays.

Lake Ewauna Trail: Klamath Avenue – Spring Street (City of Klamath Falls) – Clean up work, no delay expected.

US 97: Spring Creek Hill – Modoc Point Section (The Dalles – California Highway) – MP 240.55 – MP 257.77; No work or delay expected on this project this week.

US 97: Algoma Road – Miller Island Road Project (The Dalles – California Highway) – MP 265.65 – MP 280. 51; Paving, bridge, and striping work. Work zone controlled with flagging and pilot car, expect 20 minute delays.

FFO – US 97: Passing Lanes Project (The Dalles – California Highway_ – MP 180.06 – MP 212.13; Currently no work on this project, project work expected to start in July.

Marion County

OR 22: Tumble Creek Bridge (North Santiam) –MP 47.57 – MP 47.7; Project is complete.

Wasco County

US 97: Shaniko – Trout Creek Bridge (The Dalles – California Highway) – The contractor will be performing asphalt paving operation nightly Sunday night through Friday morning between the hours of 7 p.m. and 7 a.m. One lane of traffic will be closed using flaggers. Traffic should expect delays of up to 20 minutes. The work zone is anticipated to be between MP 68 – MP 56.5.

US 26: Kahneeta Junction (Warm Springs) – MP 91.12 – 103.09; The contractor will be performing miscellaneous cleanup and punch list work on the project. No impacts to traffic are expected.

Various

Region 4 ITS (Various) – The contractor will be installing electrical conduit and illumination foundations on the shoulders of the on-ramps and off-ramps at the Brewery Grade Interchange at MP 85 on I-84. The contractor will be closing one ramp at a time nightly from Sunday night through Friday morning between the hours of 7 p.m. to 7 a.m. Traffic should expect ramp closures and lane shifts.

Article Topic Follows: News

Jump to comments ↓

KTVZ News Team

BE PART OF THE CONVERSATION

KTVZ NewsChannel 21 is committed to providing a forum for civil and constructive conversation.

Please keep your comments respectful and relevant. You can review our Community Guidelines by clicking here

If you would like to share a story idea, please submit it here.

Skip to content