Bend Third St. underpass closing for night work
Third Street, from Burnside Avenue to Davis Avenue, will be closed for night work beginning June 30 as part of the Stormwater Infrastructure Improvement Project. Closures are nighttime only beginning at 7 p.m. and reopening to daytime traffic at 7 a.m. Detour signs will be posted during nighttime construction.
There will be no construction or closures at this location from July 3 through July 6. See schedule below:
Underpass Construction:
(nights only)
Start Date:
End Date:
Construction Hours:
Sunday, June 30
Tuesday, July 2
7 pm – 7 am
Sunday, July 7
Early September
Sundays- Thursdays,7 pm – 7 am
What to expect during night work:
Road closures – use signed detours. Travelers shoulduse caution and expect delays Construction noise and dust Construction vehicle traffic Use alternate routes to avoid construction zones
For project information, please visit bendoregon.gov/thirdstreetunderpass.