Skip to Content

Redmond road closures, delays update: Week of May 14-18

KTVZ

Here is the city of Redmond’s road closures and delays update for the week of May 14-18:

Street Maintenance Projects:

Monday, May 14 – Paving on SW 22 nd from Maple to Oak Ave., SW 15 th St. into Hope Playground, intersection closures along with flagging operations starting at 7:00 AM to finish.

Lane disruptions on SW 6th St at Deschutes Ave. for the installation of the quiet street bike crossing MMA green

Tuesday, May 15 – Paving on Canyon Maintenance path, SW Newberry, SW 25 th St., intersection closures along with flagging operations 7:00AM to finish.

Lane disruptions on SW 6th St. at Deschutes Ave. for the installation of the quiet street bike crossing MMA green

Wednesday, May 16 – Paving SW 27 th St. from Highland Ave to SW Obsidian Ave, Closure from 7:00 AM to 7:00 PM.

Thursday, May 17 – Paving SW Indian Ave. from SW 27ht St to SW 31 st St, Intersection closures along with flagging operations starting at 7:00AM until finished. Paving SW Larch Ave. from North Canal Blvd to Business 97, intersection closures along with flagging operations starting at 7:30 PM until finished.

Special Event Closures:

None

Ongoing Closures:

Historic Redmond Hotel Renovation Project

Monday, May 7 thru August 31 – from 6:00 AM to 10:00 AM Righthand lane of SW 6th St. to be partially closed from midblock between SW Deschutes Ave. and SW Forest Ave. to midblock between SW Evergreen Ave. and SW Forest Ave. The 6th St. sidewalk from SW Evergreen Ave. south to midblock will also be closed during the lane closure.

Monday, May 7 thru August 31 – from 6:00 AM to 3:30 PM Alley behind the Historic Redmond Hotel between SW 6th St. and SW 7th St. and between SW Evergreen Ave. and SW Forest Ave.

All businesses will remain open during this closure. *Activities resulting in noise will not begin until 7:00 a.m.*

South Canal Improvement Project – South Canal Blvd is closed between Wickiup Ave. and the Yew Ave. roundabout for the next few weeks. Local access is permitted. The intersection of South Canal Blvd and Wickiup Ave. will remain closed to traffic.

Scheduled Activities for the week of 5/14/2018 – 5/18/2018:

— Excavation/construct subgrade of road footprint.

— 8-inch storm system (8-inch storm pipe, drywells, & sedimentation manholes).

— Water line tie-in @ SW Wickiup Ave. planned for Monday, 5/14/2018.

o Two water services.

— Chlorination and pressure testing of new 12-inch water line from SW Wickiup Ave. to Yew Avenue roundabout.

— Removal of existing water line at SW Wickiup Ave.

— Removal of existing water line north of SW Volcano Ave to SW 23rd St.

Rebuilding the street will take 13 months, with project completion set for April 2019. Sections of South Canal Blvd. will be closed temporarily during construction, but local access to area homes and businesses will remain open. Weekly project updates can be found online at https://www.southcanalblvd.org/. Residents may call the Construction Hotline for more information or to report a concern at 541-579-2233.

Work schedules are subject to change, dependent on weather conditions and other factors.

Article Topic Follows: News

Jump to comments ↓

KTVZ News Team

BE PART OF THE CONVERSATION

KTVZ NewsChannel 21 is committed to providing a forum for civil and constructive conversation.

Please keep your comments respectful and relevant. You can review our Community Guidelines by clicking here

If you would like to share a story idea, please submit it here.

Skip to content