City of Bend road and traffic report – week of March 13-19

City of Bend

BEND, Ore. (KTVZ) -- Here is the city of Bend's road and traffic report for the week of March 13-19.

  • Butler Market Road between Eagle Road and Clyde Lane for Central Oregon Irrigation District irrigation work, full road closure with detour, 3/13/23 - 3/17/23.
  • Simpson Avenue between SW Mt. Washington Drive and SW Century Drive for a utility installation, single lane closure with flagging, 3/13/23 - 3/16/23

Ongoing Closures:

  • Neff & Purcell Improvement Project - The Neff Road and Purcell Boulevard Improvements Project is a high priority project providing both north-south connectivity and improving safety and capacity in a vital area of Bend. Project estimated to be completed mid-summer 2023. For more information visit the Neff & Purcell Improvements Project webpage.
    • Intersection of NE Neff Road and NE Purcell Boulevard for infrastructure improvements, full road closure with detour, began 2/22/23.
  • Wilson Corridor Improvements Project – Street improvements on Wilson from Second Street to 15th Street. For more information visit the Wilson Project website. This is a multiphase project with various intersections and road closures throughout its entirety.
    • Intersection of 15th Street and Wilson Avenue for roundabout construction, full intersection closure with detour, February – Early Summer 2023.
  • Newport Corridor Improvements Project – Various intersections along Newport Avenue to be closed due to removal and replacement of underground utilities. Road closures related to the project listed below. For more information, visit the Newport Corridor Improvements Project webpage. Various closures through Spring 2023.
    • NW Newport Avenue between NW 14th Street and NW College Way for the Newport Corridor Project, full road closure with detour, begins 1/9/23
  • Cooley Road between NW Brownrigg Lane and HWY 20 for initial roundabout construction, full closure with detour, begins 2/20/23.
  • ODOT Third Street Improvements â€“ Infrastructure improvements along Third Street from Butler Market Road to Greenwood Avenue. Various types of traffic control will be implemented during construction. Expected to be completed at the end of summer 2023. Street sections affected listed below.
    • Single-lane closures on Third Street near Mervin Sampels Road intersection.
  • Ferguson Sewer Project – This project is decommissioning the Camden and Ridgewater No. II Pump Stations and installing gravity sewer on Ferguson Road. Project completion fall 2023. For more information, visit the Ferguson Sewer Improvements Project webpage.
    • Ferguson Road between King Solomon Lane and Sage Creek Drive for the Freguson Sewer Project, Eastbound Lane closure with detour, begins 1/3/23

Work schedules are dependent on weather conditions and other factors. Always exercise increased caution within construction zones. Drivers should use designated detour routes. Nearby residential streets are for local traffic only.


Contact:

Deedee Fraley, Assistant City Engineer

541-385-6199, dfraley@bendoregon.gov

Paul Neiswonger, Streets Supervisor

541-317-3035, pneiswonger@bendoregon.gov


Closures and detours in Bend are updated weekly at: bendoregon.gov/traffic

Find more information about street operations at: bendoregon.gov/streetpreservation

Weekly reports can be received via email by subscribing to Weekly Road and Traffic Reports at: bendoregon.gov/enews

Article Topic Follows: Bend

Jump to comments ↓

KTVZ news sources

BE PART OF THE CONVERSATION

KTVZ NewsChannel 21 is committed to providing a forum for civil and constructive conversation.

Please keep your comments respectful and relevant. You can review our Community Guidelines by clicking here

If you would like to share a story idea, please submit it here.

Skip to content