BEND, Ore. (KTVZ) -- Here is the ODOT Region 4 construction update for the week of Dec. 30-Jan. 6.

Here at ODOT, we are committed to providing a safe and efficient transportation system for everyone. We invest in Oregon's future through roadway improvement projects. The following projects are located within Region 4; Central Oregon from The Dalles to Klamath Falls on the east side of the Cascades.

There are two ways to learn about construction taking place for the upcoming week. 

1. Visit TripCheck.com. Constantly updated with construction and crash data, TripCheck is the best way to learn about road conditions around the state. Click on a traffic cone symbol on the map to see construction impacts for that area.


2. Scroll down to the counties and highways listed below to see impacts that could affect you. Construction information is shown for one week, giving you the most up-to-date information.

All work is dependent on weather conditions, and schedules are subject to change.


HARNEY/LAKE COUNTIES

U.S. 395: Big Stick to Alkali Lake, Lakeview, Lakeview-Burns Highway (MP 15.43 - MP 46.93).

No work expected this week. 

More project information here. 

DESCHUTES COUNTY

U.S. 97 and U.S. 20 Bend North Corridor 

Continuation of on-site crushing and excavation (off road). Crews will be performing Swalley Irrigation line work off Nels Anderson by the old AVIS building and within the medians between Jamison and the U.S. 20 to 3rd St ramps (U.S. 20 MP 18.3-18.5). Short term flagging closures will occur on Jamison.
Crews will also be performing Swalley Irrigation line work within the median between SB 97 and NB 3rd St to U.S. 20 ramp (US97 MP 135.0-135.1).

More project information here.

U.S. 20: Mervin Sampels to Greenwood (3rd Street Bend, MP 18.99 – MP 20.99)

Crews will be performing lane closures on 3rd St at Mervin Sampels with day work Tuesday to Friday for sidewalk, utility and signal work. Minimal delays are expected.
Expected project completion November 2023.

More project information here.

U.S. 20: Tumalo-Cooley

Crews will be performing lane closures on U.S. 20 from Tumalo to Cooley Rd with day and potential night work Tuesday to Friday for clearing, earthworks, traffic shift, and utility works. The south leg of Old Bend Redmond Intersection and Sunset Drive remain closed. Road reconstruction along Wood Avenue, Tumalo is pending favorable weather. Minimal delays are expected. Expected project completion November 2023.

More project information here.

HOOD RIVER COUNTY

I-84: Forest Lane Over I-84 Project, Columbia River Highway (MP 46.2 - MP 46.51).

Contract work is substantially complete. No work expected this week.

More project information here.

I-84: Columbia River Highway Culverts

Crews will be performing work at various sites between Hood River and The Dalles in both the eastbound and westbound directions under single lane and shoulder closures. Single lane closures are planned to occur Monday-Thursday between MP 65 and MP 75. Travelers should expect minimal delays and use caution while traveling through the work sites. Expected completion - March 2023.

More project information here.

JEFFERSON COUNTY
and CTWS RESERVATION

U.S. 97: The Dalles - California Highway Culverts Project 

No work expected this week.

KLAMATH COUNTY

OR140 Brett Way Extension (South Klamath Falls Highway, MP 3.74 - 4.75)

No work expected this week. 

More project information here.

OR 140 at OR66 Intersection Improvements Project 

No work expected this week.

More project information here

U.S. 97: OR 58 - California Border Project (The Dalles - California Highway, MP 252.44 - MP 278.81)

No work expected this week. 

More project information here.  

WASCO COUNTY (OR)/KLICKITAT (WA)

The Dalles (Columbia River) Bridge Project (U.S. 197: WA MP 0.57 I-84: MP 100.6-U.S. 197:OR  MP 0.61 I-84: MP 102.2.)

Weekend full closures of the bridge continue each weekend starting Thursday evenings at 8 p.m. to Monday mornings at 6 a.m. Designated detour route during full closures is via  I84/U.S. 97 @ Biggs Jct./SR14. Outside of the full closure timeframes, work continues to occur on the shoulders and staging areas off the ends of the bridge during daytime hours with no impacts to traffic, as well as on the bridge deck, sidewalks and under the bridge during weeknights under single lane closures controlled by flaggers. A speed reduction to 35 mph is in place across the bridge. Use caution when traveling through the project. Anticipated completion - Spring 2023.

More project information here.

Watch a video on this project here. 

 Questions or comments?

Meghan Blyth, ODOT Community Affairs Coordinator 

(541)280-2716 or Meghan.Blyth@odot.oregon.gov

For current road and weather conditions visit TripCheck.com or call 511

Article Topic Follows: Community Billboard

Jump to comments ↓

KTVZ news sources

BE PART OF THE CONVERSATION

KTVZ NewsChannel 21 is committed to providing a forum for civil and constructive conversation.

Please keep your comments respectful and relevant. You can review our Community Guidelines by clicking here

If you would like to share a story idea, please submit it here.

Skip to content