The first stage of the Reed Market project will be complete and open to traffic Friday, Sept. 6, city official said. Reed Market will be open from Newberry Drive (the Senior Center) to Teakwood Drive. Admiral Way and Teakwood Drive will be open to local traffic.

The second stage of the Reed Market project will begin Friday, September 6. Reed Market will be closed from Shadowood Drive to west of Orion Drive, Orion Drive will remain open. The closure is required to continue the re-construction of Reed Market Road. The work is being be performed by local contractor Jack Robinson & Sons.

A temporary, signed detour route for Reed Market through traffic will be in effect for the duration of construction. Traffic will continue to utilize SE15th Street, NE Bear Creek Road, SE 27 th Street and SE Ferguson Road.

Email questions or comments to streetbond@ci.bend.or.us, or call the project hotline at 541-388-5547.

For more information, visit www.bendoregon.gov/GOBond.

Article Topic Follows: News

Jump to comments ↓

KTVZ News Team

BE PART OF THE CONVERSATION

KTVZ NewsChannel 21 is committed to providing a forum for civil and constructive conversation.

Please keep your comments respectful and relevant. You can review our Community Guidelines by clicking here

If you would like to share a story idea, please submit it here.

Skip to content