ODOT Region 4 construction update: Week of Nov. 8-12

ODOT

BEND, Ore. (KTVZ) -- Here is the ODOT Region 4 construction report for the week of Nov. 8-12.

The Oregon Department of Transportation is committed to providing a safe, efficient transportation system. ODOT invests in Oregon's future through roadway improvement projects. The following projects are located within ODOT's Region 4 encompassing Central Oregon from The Dalles to Klamath Falls on the east side of the Cascades.

All work is dependent on weather conditions, and schedules are subject to change.

Deschutes County

U.S. 97: S Century Drive to USFS border (MP 153.11-MP 156.26)The contractor has installed a detour lane shift to route traffic around the structure excavation. Traffic should use caution when traveling through the work and traffic pattern change. No delays to traffic are anticipated.

U.S. 97: Nels Anderson Place - Romaine Village Way. Construct new ADA ramps along the parkway, repave all travel lanes and exit/entrance ramps (MP134.84-MP141.12).

Contractor will not be working on project this week.

Harney/Lake counties

US395: Big Stick – Alkali Lake, Lakeview, Lakeview-Burns Highway (MP 15.43- MP46.93). Clean-up work is scheduled between MP 35-47. Expect minor delays.

Klamath County

OR140 Brett Way Extension (South Klamath Falls Highway, MP3.74-4.75) The roundabout is open. Sign installation and clean-up work is scheduled. Expect minor delays.

Jefferson County
and CTWS Reservation

U.S. 26: Warm Springs Safety Corridor, (MP 103.02-MP111.16) .Contractor will be performing construction activities during the daytime, they will perform seeding, grading and concrete activities. The highway will be reduced to one travel lane during the daytime which will be controlled by flaggers and a pilot car with a half mile work zone occuring anywhere between MP 103.02 - MP 111.16 . Traffic can expect delays of up to 20 minutes during the work hours.

Wasco County (OR)/Klickitat (WA)

The Dalles (Columbia River) Bridge Project (U.S. -197: WA MP 0.57 I-84: MP100.6-U.S. 197:OR  MP 0.61 I-84: MP 102.2.)Bridge construction is occurring, requiring full closure of The Dalles (Columbia River) Bridge between Washington and Oregon from 8 pm on Thursdays – 6 am on Mondays. Use an alternate route. The established, signed detour route is via I84, US97 at Biggs Jct. and SR14 to the east. Full bridge closures will occur every weekend between September 9, 2021 and May 23, 2022, except for the weekends of Thanksgiving, Christmas and  New Years. Additionally, crews will be working overnight (Mon - Wed nights); expect delays up to 20 minutes during nighttime hours while flaggers control traffic across the bridge. Crews will continue bridge deck replacement and continue forming new concrete panels at their pre-cast yard location.

Wasco County/CTWS Reservation

US26: Clear Lake Road – NW Dogwood Lane, Warm Springs Highway, (MP 66.43-112.91).

No work planned this week.

Wheeler County

U.S.26: Bridge Creek Bridge Project (U.S. 26/Ochoco Highway, milepost 64.91-65.19)

All work will be off of roadway with no impacts to traveling public, contractor will be replacing storm pipe.

Article Topic Follows: Community Billboard

Jump to comments ↓

Author Profile Photo

Barney Lerten

Barney is the digital content director for NewsChannel 21. Learn more about Barney here.

BE PART OF THE CONVERSATION

KTVZ NewsChannel 21 is committed to providing a forum for civil and constructive conversation.

Please keep your comments respectful and relevant. You can review our Community Guidelines by clicking here

If you would like to share a story idea, please submit it here.

Skip to content