BEND, Ore. (KTVZ) -- Here is the ODOT Region 4 construction report for the week of Nov. 29-Dec. 3.

The Oregon Department of Transportation is committed to providing a safe, efficient transportation system. ODOT invests in Oregon's future through roadway improvement projects. The following projects are located within ODOT's Region 4, encompassing Central Oregon from The Dalles to Klamath Falls on the east side of the Cascades.

All work is dependent on weather conditions, and schedules are subject to change.

RWIS sign

Intelligent signs delivering real time information.

Ward/Hamby roundaboutConstruction of the Ward/Hamby roundabout on U.S. 20 east of Bend is now under way, though earthwork likely  won't begin until spring.

Deschutes County

U.S. 97: Road Weather Management Project (MP143.68--MP164.17).

ODOT will install Road and Weather Information System (RWIS) speed sensors, travel time readers and changeable message signs. The contractor will be working on the shoulder this week. No impact to traffic.

U.S. 97: S Century Drive to USFS border (MP 153.11-MP 156.26)The contractor will be working on the U.S. 97 southbound alignment installing the new southbound wildlife undercrossing. The contractor has installed a detour lane shift to route traffic around the structure excavation. Traffic should use caution when traveling through the work and traffic pattern change. No delays to traffic are anticipated.

US97: Nels Anderson Place – Romaine Village Way (MP134.84 – MP141.12)

Construct new ADA Ramps along the Parkway, repave all travel lanes and entrance/exit ramps of the parkway, and re-stripe the roadway after paving is complete. Contractor will be performing Reed Market Interchange closures to install crosswalk legends.

ALL CLOSURES AND WORK WILL OCCURE BETWEEN 9 p.m. and 6 a.m.

U.S. 97 Redmond-Bend (MP124.4-MP133.51)

ODOT will construct the following as part of the project: deceleration lanes at Quarry Avenue and 61st Street from U.S. 97 southbound, acceleration lane from 61st Street to U.S. 97 southbound to provide greater merge distance, median barrier installation south of the Tumalo Road Interchange, and a turnaround from U.S. 97 southbound to northbound, install reflective pavement markers added for improved lane separation, and remove rock outcropping removal near the edge of the roadway for improved visibility. The contractor will be working on the shoulder this week. No impact to traffic.

U.S. 20: Mervin Sampels – Greenwood (3rd Street Bend, MP18.99 – MP20.99)

ODOT will construct the following: new pavement in the project limits, update sidewalks, bike lanes and ADA ramps. Update signals, storm water and drainage features, illumination devices, and ITS equipment. Update bus stop locations, install new signs, update crosswalks and install rapid flashing beacon crossings. The contractor will be installing hard barrier from Mervin Sampels to River Mall Road starting Tuesday, Nov. 30. The hard barrier will close the fast lane in the North/South direction including the middle turn lanes. The lane closure will be in place on 3rd Street (U.S. 20/U.S. 97 Business route) until March 1, 2022. The contractor will work inside the barrier installing new drainage features.

U.S. 20: Ward/Hamby Rd. Intersection Project (MP3.26-MP3.86)

ODOT will construct a single-lane roundabout at the intersection of U.S. 20 and Ward/Hamby roads.

The contractor will be working on the shoulder this week. No impact to traffic.

Harney/Lake counties

US395: Big Stick – Alkali Lake, Lakeview, Lakeview-Burns Highway (MP 15.43- MP46.93). Clean-up work is scheduled between MP 35-47. Expect minor delays.

Klamath County

OR140 Brett Way Extension (South Klamath Falls Highway, MP3.74-4.75) Traffic change. The roundabout is open. Paving and rock work is scheduled on Brett Way. Expect minor delays at the intersection of Homedale Road and Airway Drive.

Warm Springs Safety Corridor

Warm Springs Safety Corridor

Jefferson County
and CTWS Reservation

U.S. 26: Warm Springs Safety Corridor, (MP 103.02-MP111.16) .

The contractor will be performing construction activities during the daytime; they will perform seeding, grading and concrete activities. The highway will be reduced to one travel lane during the daytime which will be controlled by flaggers and a pilot car with a half-mile work zone occurring anywhere between MP 103.02 - MP 111.16. Traffic can expect delays of up to 20 minutes during the work hours.

Wasco County (OR)/Klickitat (WA)

The Dalles (Columbia River) Bridge Project (U.S. -197: WA MP 0.57 I-84: MP100.6-U.S. 197:OR  MP 0.61 I-84: MP 102.2.)

Bridge construction is occurring, requiring full closure of The Dalles (Columbia River) Bridge between Washington and Oregon from 8 p.m. on Thursdays – 6 a.m. on Mondays. Use an alternate route. The established, signed detour route is via I-84, US97 at Biggs Jct. and SR14 to the east. Full bridge closures will occur every weekend between September 9, 2021 and May 23rd, 2022, except for the weekends of Thanksgiving, Christmas and New Year’s. Crews will continue bridge deck replacement and continue forming new concrete panels at their pre-cast yard location.

Wasco County/CTWS Reservation

US26: Clear Lake Road – NW Dogwood Lane, Warm Springs Highway, (MP 66.43-112.91).

No construction work this week.

Wheeler County

U.S.26: Bridge Creek Bridge Project (U.S. 26/Ochoco Highway, milepost 64.91-65.19)

No project work this week.

Article Topic Follows: Community Billboard

Jump to comments ↓

KTVZ news sources

BE PART OF THE CONVERSATION

KTVZ NewsChannel 21 is committed to providing a forum for civil and constructive conversation.

Please keep your comments respectful and relevant. You can review our Community Guidelines by clicking here

If you would like to share a story idea, please submit it here.

Skip to content