ODOT Region 4 construction update: Week of July 22-29

ODOT

BEND, Ore. (KTVZ) -- Here is the Oregon Department of Transportation Region 4 weekly construction update for the week of July 22-29.

Here at ODOT, we are committed to providing a safe and efficient transportation system for everyone. We invest in Oregon's future through roadway improvement projects. The following projects are located within Region 4; Central Oregon from The Dalles to Klamath Falls on the east side of the Cascades.

There are two ways to learn about construction taking place for the upcoming week. 

1. Visit TripCheck.com. Constantly updated with construction and crash data, TripCheck is the best way to learn about road conditions around the state. Click on a traffic cone symbol on the map to see construction impacts for that area.

2. Scroll down to the counties and highways listed below to see impacts that could affect you. Construction information is shown for one week, giving you the most up-to-date information.

All work is dependent on weather conditions, and schedules are subject to change.


DESCHUTES COUNTY

U.S. 97: South Century Drive to USFS border (MP 153.11 - MP 156.26)

Crews will be preforming day work Monday to Friday with single lane closures. Expect minimal delays to traffic. Expected completion end of August 2022.

More project information here.

Watch a video on this project here. 

U.S. 97: Road Weather Management Project (MP 143.68 - MP 164.17)

Crews will be performing day work Monday to Friday consisting of shoulder work to complete installation of items for the project, expect no delays to traffic. Expected Completion end of August 2022

More project information here.

U.S. 20: Mervin Sampels to Greenwood (3rd Street Bend, MP 18.99 – MP 20.99)

Crews will be performing single lane closures on 3rd St. from Butler Market to Mervin Sampels with day and night work Monday to Friday. Contractor will also be continuing reconstruction of the intersection of 3rd and Greenwood, with single lane closures in place Sunday - Thursday Night 7pm - 7am. Expect delays. Expected Completion November 1st 2023.

More project information here.

U.S. 97 Redmond-Bend Safety Improvements (MP 124.4 - MP 133.51)

Crews will be performing day work Monday to Friday consisting of shoulder work. Expect no delays to traffic. Expected Completion August 12th 2022, except seeding.

More project information here.

U.S. 20: Ward/Hamby Road Roundabout (MP 3.26 - MP 3.86)

Crews will be performing day work Monday to Friday consisting of shoulder work. Expect no delays to traffic. Expected Completion end of July 2022, except seeding.

More project information here.

Watch a video on this project here. 

CLAKAMAS COUNTY

US26: SE Kelso Rd-Frog Lake Sno Park Sec

Crews will be performing clearing and erosion control between mile point 27.11 - 38.01 daytime hours, with shoulder closures as well as possible single lane closures. Possible lane closures with flagging impacting side streets at MPs 33.27 (SE Alder Creek Rd.), 34.92 (E. Sleepy Hollow Dr.), 36.43 (E. Peter Place), 36.53 (E. Sun Rae Dr ) and 36 79 (E Brightwood Loop Rd) Expected Completion Sept 2022.

HARNEY/LAKE COUNTIES

U.S. 395: Big Stick to Alkali Lake, Lakeview, Lakeview-Burns Highway (MP 15.43 - MP 46.93).

Grinding, in-place cement treated base, paving and pipe work from MP 15.4 to MP 20.3, 24 hour flagging and pilot car 7 days a week, expect 20 minute delays.

More project information here. 

HOOD RIVER COUNTY

I-84: Forest Lane Over I-84 Project, Columbia River Highway (MP 46.2 - MP 46.51).

Full closure of bridge on NW Forest Lane continuing through July 26th. Frontage Road will have daytime lane closures with flagging. Crews will continue to build embankment, remove and place material for reconstruction of Frontage Road and install rebar and formwork for bridge approaches. Expected Project Completion July 29th, 2022

More project information here.

JEFFERSON COUNTY
and CTWS RESERVATION

U.S. 26: Clear Lake Road - NW Dogwood Lane Project

CTWS RESERVATION, WASCO COUNTY: At MP 69, traffic is now in detour route next to existing bridge. Crews will be building forms and rebar for a new foundation. Watch for trucks going in and out of work zone. Narrowed lane widths and a speed reduction to 40mph are in place. Expected Completion December 2022.

More project information here.

Watch a video on this project here. 

U.S. 97: The Dalles - California Highway Culverts Project 

Pipe work at MP 267.41 to MP 268.73, 24 hour flagging zone Monday thru Friday expect 20 minute delays.

KLAMATH COUNTY

OR140 Brett Way Extension (South Klamath Falls Highway, MP 3.74 - 4.75)

Earthwork, paving, curbs and pipe work on Brett Way and Wings Way, expect minor delays.

More project information here.

U.S. 97: OR 58 - California Border Project (The Dalles - California Highway, MP 252.44 - MP 278.81)

Bridge work on Nevada Street Bridge at MP 273.62, USBR Bridge at MP 273.71, and the Green Spring Bridge at MP 277.12.
Nevada Street/Oregon Avenue: lane shift traffic control installed, bridge work will be done behind concrete barrier, no delays expected.
US97: lane shift traffic control installed, bridge work will be done behind the barrier, no delays expected.


More project information here.  


WASCO COUNTY (OR)/KLICKITAT (WA)

The Dalles (Columbia River) Bridge Project (U.S. 197: WA MP 0.57 I-84: MP 100.6-U.S. 197:OR  MP 0.61 I-84: MP 102.2.)

WASCO COUNTY, SHERMAN COUNTY (OR) / KLICKITAT COUNTY (WA): The weekend full closures of The Dalles bridge have ended, with the expectation to resume closures after Labor day in the fall. Crews continue repair work on concrete panels at their pre-cast yard location and structure preparation underneath. Work will also be occurring on shoulders and staging areas off the ends of the bridge during week days with no delays anticipated, use caution when traveling through the project. Expected Completion TBD.

More project information here.

Watch a video on this project here. 

I-84: Corbett Interchange - Multnomah Falls Section

Single lane closures will occur nightly. Contractor will clean and perform new lining procedures on existing pipes. Expected Completion Sept. 2022

More project information here

Questions or comments?

Meghan Blyth, ODOT Community Affairs Coordinator 

(541)280-2716 or Meghan.Blyth@odot.oregon.gov

For current road and weather conditions visit TripCheck.com or call 511

Article Topic Follows: Community Billboard

Jump to comments ↓

KTVZ news sources

BE PART OF THE CONVERSATION

KTVZ NewsChannel 21 is committed to providing a forum for civil and constructive conversation.

Please keep your comments respectful and relevant. You can review our Community Guidelines by clicking here

If you would like to share a story idea, please submit it here.

Skip to content